November 16, 2026:


Utilities in 53 US service territories have signed contracts to deliver about 120 gigawatts (GW) of electricity to data centers, only 22% of the 537 GW they report in their pipelines, according to data Latitude Media published Friday, Nov. 13. Utilities are already soliciting about 37 GW of new generation, and ratepayers could end up covering part of that bill depending on how each region allocates the costs.
The 120 GW is about 5.5 times the 22 GW of data center load operating in those same territories today. The figures come from Latitude Intelligence, a research platform Latitude Media launched this month that tracks each covered utility’s data center load by stage, including operating, signed, and reported. Latitude Media detailed the platform in its Latitude Intelligence launch post.
Utilities disclose data center demand in earnings calls, resource plans, and regulatory filings, and Latitude Media’s analysis of commitments shows they don’t count it the same way. Some report every inquiry, while others report only executed agreements. Latitude Intelligence applies one definition: load counts as signed when the customer has an executed agreement to take service.
The gap is widest at some of the biggest names. Georgia Power reports 80.1 GW of data center load but has signed 12.8 GW, according to the platform.
Jefferies analysts reached a similar conclusion with a different method, sorting 187 GW of disclosed commitments across regulated utilities into tiers by contract strength. Under the strictest tier, formal electric service agreements only, the total fell to 69 GW.
Latitude expresses some figures as a share of a utility’s current peak demand. AEP Ohio’s signed load equals 235% of its peak. NIPSCO in northern Indiana sits at 169% and PPL in Pennsylvania at 145%.
At each of those utilities, signed load exceeds the most power the utility currently draws at once. AEP Ohio and PPL operate in PJM Interconnection’s footprint, covered below, while NIPSCO sits in a different grid, the Midcontinent Independent System Operator (MISO).
Dominion Energy reported a 54.9 GW pipeline of data center capacity in its third-quarter results, up 13% since December, according to Baxtel. Dominion described the capacity as “in various stages of contracting,” according to Zacks’ earnings coverage.
Dominion’s own filing with PJM’s Load Analysis Subcommittee splits roughly 54 GW into tiers. About 12.0 GW is under electric service agreements and 9.4 GW has construction letters of authorization, and Dominion classes both as firm. The remaining 32.5 GW holds engineering letters of authorization, which Dominion does not classify as firm, and it includes only 41% of it in its forecast.
TechTimes reported in May that Dominion had roughly 51 GW of data center capacity under contract as of March.
A signed agreement is only as strong as its exit terms. In the 15-year contract NIPSCO filed with Indiana regulators for Amazon, Amazon holds a one-time option to cut its total capacity by 1,200 MW by March 31, 2029, according to Utility Dive. The Indiana Utility Regulatory Commission fully approved the Amazon special contract on June 17, according to NiSource, which said the structure is designed so data center customers fund the generation and transmission they need. FactSet reported the filing also requires Amazon to pay defined costs if it ends its projects and includes a parent company guarantee, though the amounts are not public.
Courts treat such take-or-pay clauses unevenly. Outside oil and gas, enforceability can turn on whether the parties freely negotiated the terms, and courts sometimes reject such clauses as penalties. If plants are built for load that later shrinks, the result is a stranded asset: an investment that cannot earn its expected return before the end of its economic life. NIPSCO’s structure walls off generation costs from other customers through a separate affiliate called GenCo, and NiSource says this protects existing customers.
Georgia regulators faced a similar question. Georgia Public Service Commission staff raised concerns about unsigned contracts and stranded assets, T&D World reported, and the resulting agreement requires Georgia Power to financially back the expected new load. Existing customers are shielded from the costs of serving new data centers even if projected demand does not materialize, the same report says.
Across the six largest utilities Latitude tracks, about 37 GW of new generation is out for bid or under consideration. Dominion is seeking up to 7.3 GW of dispatchable generation, with proposals due by 5 p.m. Dec. 18. Georgia Power is pursuing 2 to 6 GW of additional dispatchable capacity, AEP has 4 GW solicitations open at Indiana Michigan Power and at Public Service Company of Oklahoma, and Xcel has multi-gigawatt procurements underway, according to Latitude’s tally. The Georgia commission voted 5-0 on Dec. 19, 2025 to approve a stipulated agreement allowing Georgia Power to add 9,885 MW, most of it for large new customers such as data centers.
For projects energized since late 2021, the average gap between public announcement and first power was about 33 months, per Latitude. The sample is small: the platform has data for 19 projects, and the average rests on 14 after excluding outliers. On that record, a project announced today would draw grid power around August 2029, and only if it reaches a signed agreement.
PJM utilities including PPL Electric, FirstEnergy and AES Ohio cut their near-term large-load forecasts by a combined 6.5 GW, according to a Jefferies note reported by Utility Dive. Jefferies estimated the revisions could shrink PJM’s planned one-time reliability backstop procurement to as little as 630 MW, from an initial target of about 6.8 GW.
PJM’s independent market monitor, Monitoring Analytics, estimates that data center load added $29.4 billion in capacity costs across the last four base auctions, 46% of $63.6 billion in total. That figure is the monitor’s own estimate. Monitor President Joseph Bowring argues data center load should be removed from the capacity market and procured through a dedicated auction so data centers pay for their own capacity, The Hill reported.
The previous PJM auction, for 2028/2029 delivery, cleared at the $325 per megawatt-day price cap in all zones, the third straight PJM auction to hit the cap. The next auction, for 2029/2030 delivery, is scheduled to run from Dec. 9 to Dec. 15.
Capacity markets work by forecast: a higher peak forecast raises the amount grid operators buy, and the clearing price reaches customers through supply charges. That makes the gap between reported and signed load a cost question, not only an accounting one.
On June 18, the Federal Energy Regulatory Commission issued show-cause orders to six regional grid operators, directing them to justify or reform the tariff rules that govern how data centers and other large loads connect. FERC found it has exclusive jurisdiction over the rates, terms, and conditions of interstate transmission service to large loads, while states keep authority over retail sales, siting, and construction, according to Troutman.
On Aug. 14, FERC granted abeyance motions from PJM and certain transmission owners, which moved PJM’s response date to Nov. 16. Responses from five grid operators, including PJM and MISO, are due Monday, Nov. 16, and Southwest Power Pool’s are due Nov. 20. A grid operator that files its own Section 205 tariff proposal by Nov. 16 suspends its obligation to answer the show-cause order directly, but only for respondents that file.
The filings will show how each region defines a large load, what study clocks it proposes and who pays for upgrades. Cost allocation is among the sharpest issues FERC put before grid operators.
Gov.-elect Keisha Lance Bottoms said Georgia should take a pause on data centers at a Cobb County press conference, citing effects on the environment and utility bills. After the election she said “all things related to data centers will be on the table,” according to Georgia Public Broadcasting. Democrats won Georgia utility board seats, giving them a majority on the Georgia Public Service Commission, Fox 5 Atlanta reported.
Outgoing Gov. Brian Kemp called a moratorium irresponsible and said local communities rather than the state should decide whether data centers are built. Bottoms’s record is not purely restrictive: Invest Atlanta approved up to $440 million in bonds, a lease-purchase property tax incentive and a 10-year abatement worth more than $5 million for the Coda data center in 2018, unanimously, with Bottoms as mayor and board chair, the AJC reported. Bottoms has also said her Republican rival, Rick Jackson, holds a financial stake in Data Hub Developers, which is proposing a hyperscale facility in Bowie County, Texas, according to WTOC’s report on the clash.
The question for Georgia is whether the 12.8 GW signed or the 80.1 GW reported is the number that regulators and the next governor plan around.
Ohio voters decided 23 local data center measures, counting Wilmington’s four questions separately, according to the Statehouse News Bureau’s tally. By that tally, 19 restrictions or regulations passed, and two recall measures targeting four officials in Piqua and Urbana passed. Two measures that would have opposed development, a Monroeville advisory question and an Ashville referendum, failed. Latitude reports that a proposed statewide constitutional amendment restricting certain data centers is gathering signatures for a ballot next fall.
None of these votes cancels signed contracts. They bear on how much of the 537 GW of reported load converts, and on whether utilities win approval for the generation they are soliciting.
Reported load is demand a utility discloses in pipelines, which can include inquiries. Signed load requires a customer’s executed agreement to take service. Latitude counts 120 GW signed against 537 GW reported.
No. Contracts can carry reduction options and termination payments, as in NIPSCO’s Amazon contract, and courts enforce such clauses unevenly outside oil and gas. A signed agreement is a stronger commitment than an inquiry, not a guarantee.
It depends on how your region allocates costs. In PJM, the market monitor attributes $29.4 billion of capacity costs over four auctions to data center load, while in Indiana NiSource says its separate-affiliate structure shields existing customers.
Dominion’s 54.9 GW pipeline includes engineering authorizations that are not classed as firm, plus construction authorizations and service agreements that are. Dominion’s PJM filing shows about 12.0 GW under service agreements.